Connect with us

State News

RTD threatens action against contractor for beleaguered N-Line to Thornton

Regional Transportation District officials on Wednesday threatened to file a formal notice of default to the contractor building the N-Line commuter rail from downtown Denver to Thornton, the opening of which has been delayed for more than a year.

In a press release, RTD said it is contemplating the action against Regional Rail Partners “due to the contractor’s continued delays in meeting project milestones and inability to fulfill its contractual obligations.”

RTD said the delays already experienced mean the N-Line won’t open before August. The 13-mile line will also serve Northglenn and Commerce City with six stations.

“I commend the RTD board for finally standing up to the contractor,” Commerce City Mayor Benjamin Huseman told The Denver Post. “It’s been too long that the contractors are allowed to run around and not meet deadline.”

RTD said Regional Rail Partners, which is a joint venture of Balfour Beatty Rail Infrastructure and Graham Contracting, “has failed to meet several target dates for project turnover, the latest being Feb. 3, and the project schedule continues to be affected.”

The “contractor has yet to reach substantial completion on the project and turn the corridor over to RTD,” the release stated. Work began on the N-Line, which is an electrified commuter rail line akin to the University of Colorado A-Line, nearly six years ago and was supposed to open to passengers in 2018.

A request for comment from the Westminster-based contractor was not immediately returned.

Angie Rivera-Malpiede, chair of RTD’s board of directors, said “the fact that this project is still not complete is completely unacceptable and frustrating to not only us at RTD, but to our stakeholders and the public we serve.”

The threatened legal action follows a similar move by RTD against the contractor building the G-Line to Arvada and Westminster. In 2018, the agency threatened to terminate its contract with Denver Transit Partners, saying at the time that the long-delayed opening of the G-Line “is unacceptable to RTD.”

That action followed a lawsuit that Denver Transit Partners filed against RTD, in which the contractor claimed that RTD owed it tens of millions of dollars for costs incurred over the timing of crossing gates that failed for years to get regulatory approvals from federal and state officials.

The G-Line finally opened last April.

Trending